Dalrymple Bay Infrastructure Site Visit Presentation November 2026

27 slides

Part of Investor presentation examples · Australian investor presentation examples

This is Dalrymple Bay Infrastructure's (ASX: DBI) November 2026 Dalrymple Bay Terminal site visit presentation, lodged with the ASX on 24 November 2026. It introduces the terminal, a metallurgical coal export facility at the Port of Hay Point in Queensland, Australia, covering its history, customers and take-or-pay contracts, competing Queensland coal ports and AME market outlook charts. It then walks through the terminal's physical layout (inloading, stockyard, outloading, jetty and berths) and the non-expansion capital expenditure (NECAP) programme, including the shiploader and stacker-reclaimer replacements, the Terminal Infrastructure Charge outlook and the 8X expansion. Appendices cover roles and responsibilities, a glossary and the disclaimer. Amounts are Australian dollars (A$) unless stated otherwise.

11 likes
0 downloads

Uses this deck’s cover as a style reference for slides made from your own content. Or pick any page below to use its layout as the reference.

Quick Navigation

Tags

Dalrymple bay infrastructure
Dbi
Asx
Investor presentation
Site visit presentation

Share the slides

Description

Main Topic

This is Dalrymple Bay Infrastructure's (ASX: DBI) November 2026 Dalrymple Bay Terminal site visit presentation, lodged with the ASX on 24 November 2026. It introduces the terminal, a metallurgical coal export facility at the Port of Hay Point in Queensland, Australia, covering its history, customers and take-or-pay contracts, competing Queensland coal ports and AME market outlook charts. It then walks through the terminal's physical layout (inloading, stockyard, outloading, jetty and berths) and the non-expansion capital expenditure (NECAP) programme, including the shiploader and stacker-reclaimer replacements, the Terminal Infrastructure Charge outlook and the 8X expansion. Appendices cover roles and responsibilities, a glossary and the disclaimer. Amounts are Australian dollars (A$) unless stated otherwise.

Key Benefits

  • •Gives a plain-language tour of a large coal export terminal, from rail inloading to shiploading
  • •Shows contract terms, customer list and access-queue information in one place
  • •Explains how NECAP spending is added to the asset base and linked to the Terminal Infrastructure Charge (TIC)
  • •Includes key operating metrics such as 84.2Mtpa capacity, 12 yard machines and 4 berths
  • •Provides a clear roles-and-responsibilities map between DBI, the DBT Operator, NQBP and rail parties

Target Audience

  • •Equity and fixed-income analysts covering Australian infrastructure
  • •Site-visit attendees and investor relations teams
  • •Port, bulk-handling and mining logistics professionals
  • •Students and researchers studying Queensland coal export infrastructure
  • •Presentation designers looking for an infrastructure or site-visit deck reference

Use Cases

  • •Preparing for or following up a Dalrymple Bay Terminal site visit
  • •Reference for terminal operations terminology and equipment specifications
  • •Template inspiration for infrastructure asset overview decks
  • •Comparing Queensland coal port capacity and access arrangements
  • •Understanding a regulated or light-handed access-charge structure

Unique Value Propositions

  • •Combines aerial photography, annotated site layouts and equipment specifications on a consistent teal template
  • •Pairs operational detail with the capital programme and pricing mechanics on the same deck
  • •Dated facts such as SL1A commissioning in November 2026 and the access queue as at 31 October 2026
  • •Full appendix set including roles matrix, glossary and legal notices

Slide Pages (27)

Detailed view of each slide page, including layout, key content and visual elements.

Page 1
title slide

Dalrymple Bay Terminal Site Visit, November 2026

Content

Title slide for the Dalrymple Bay Terminal Site Visit presentation dated November 2026, carrying the Dalrymple Bay Infrastructure logo.

Layout Structure

A dark teal panel with a rounded top-right corner holds the logo, title and date on the left, while a two-part aerial photo of ships at the jetty fills the right.

Key Visual Elements

  • •DBI logo
  • •Teal rounded panel
  • •Aerial photo of ships at coal jetty
  • •Vertical 'personal use only' watermark
Page 2
KPI dashboard

Dalrymple Bay Infrastructure

Content

DBI, through its foundation asset Dalrymple Bay Terminal (DBT), aims to provide safe and efficient port infrastructure for Australian metallurgical coal exports. Key facts listed include the largest global met coal export facility by contracted volume, a 14% share of 2025 global seaborne met coal exports (AME), 84.2Mt fully contracted on a 100% take or pay basis, a $4.02/t Terminal Infrastructure Charge, 100% pass-through of operating and maintenance costs, 84% of revenue from predominantly metallurgical coal mines, 10 customers across 21 mines and current pricing arrangement expiry in 2031. This is the first slide to show money; the deck's glossary and disclaimer state dollars are Australian.

Layout Structure

A banded list of eight large headline figures with descriptions sits on the left, with a full-height photo of a ship at the jetty on the right and footnotes below.

Key Visual Elements

  • •Eight headline metrics
  • •Striped metric rows
  • •Jetty and ship photo
  • •Five footnotes
Page 3
table

History of DBT

Content

The terminal was commissioned in 1983 at the Port of Hay Point, about 38km south of Mackay and 900km north of Brisbane. It was privatised in 2001 under a 99-year lease, Brookfield bought it from Prime Infrastructure in 2009 and DBI listed on the ASX in December 2020. A table shows capacity growing in phases to 84.2Mtpa after 7X in 2009.

Layout Structure

Bullet points on the left sit beside a teal-headed expansion table on the right listing phase, date, incremental capacity and terminal capacity.

Key Visual Elements

  • •Expansion phase table
  • •Bulleted history
  • •Footnote citing 2018 capacity estimates
Page 4
map

The DBT services predominantly metallurgical coal mines in the Bowen Basin

Content

DBT services 21 mines across the Central Bowen Basin and is about 144km from the estimated catchment centre (Coppabella), versus 305km to Abbot Point and 536km to Gladstone. The slide states Goonyella system train payloads are about 20% higher than the Blackwater system and about 50% higher than the Abbot Point route.

Layout Structure

A labelled regional map with rail systems, ports and customer mines sits on the left and a bulleted comparison of haul distances and payloads on the right.

Key Visual Elements

  • •Queensland coast map
  • •Rail system lines
  • •Map legend
  • •Port capacity labels
  • •Indicative-only note
Page 5
table

Terminal Customers and contracts

Content

DBT is fully contracted at 84.2mtpa to 30 June 2028 under take-or-pay contracts, with evergreen extension options to be exercised at least 12 months before expiry. A table lists the customers (Anglo American, Argo Resources, Glencore, Middlemount Coal, QMetco, Peabody, Pembroke Resources, Stanmore Resources, TerraCom and Whitehaven Coal) and their mines, as at 31 October 2026. The small-print footnote on socialisation is dense but legible.

Layout Structure

Contract-term bullets sit on the left and a two-column customer and mine table on the right, with four footnotes along the bottom.

Key Visual Elements

  • •Customer and mine table
  • •Contract bullets
  • •Dense footnotes
Page 6
table

Queensland Coal Ports

Content

DBT is presented as a low cost export pathway for central Bowen Basin mines. The table compares DBT (84.2Mtpa, fully contracted to June 2028), HPCT (55Mtpa, BMA only), NQXT (50Mtpa), WICET (27Mtpa) and RG Tanna (75Mtpa) by owner, location, access status, coal regions and comments.

Layout Structure

A full-width teal-headed comparison table with seven columns and five terminal rows occupies the slide.

Key Visual Elements

  • •Seven-column comparison table
  • •Capacity column
  • •Access status column
Page 7
data visualization

DBT is strategically positioned to unlock high quality Bowen Basin coal reserves

Content

Three AME-sourced charts (AME Coal Data Pack, July 2026) cover forecast global crude steel production by region, export metallurgical coal demand and export met coal supply. The supply waterfall runs from 367mt in 2025 to 441mt in 2040, with Australia contributing +73mt. The bar charts for 2020, 2030e and 2040e carry no data labels, so their values are not quoted here.

Layout Structure

Three side-by-side columns each pair a headline statement with a chart, separated by vertical rules, with a source line at the bottom.

Key Visual Elements

  • •Two stacked bar charts
  • •Waterfall chart
  • •China, India, S.E Asia, ROW legend
  • •Source note
Page 8
section divider

DBT Overview

Content

Section divider introducing the DBT Overview part of the presentation.

Layout Structure

A teal rounded panel on the left carries the white section title, with a wide landscape photo of the stockyard and rail loop dam on the right.

Key Visual Elements

  • •Teal panel
  • •Stockyard aerial photo
  • •Section title
Page 9
KPI dashboard

Safety

Content

DBI states it was the first Australian organisation awarded Safety Citizenship, the highest safety culture rating applied by Sentis. It reports zero fatalities, serious injuries and high potential incidents for its employees and contractors on NECAP projects in FY25, and notes that the DBT Operator had no fatalities, 1 serious injury and 8 HPIs in 2025. Management also have a short-term incentive gateway tied to group-wide safety objectives.

Layout Structure

Four equal rounded cards with dotted outlines and small icons present one large-type safety statement each across the page.

Key Visual Elements

  • •Four dotted-outline cards
  • •Line icons
  • •Highlighted teal key words
Page 10
map

DBT Overview (annotated aerial)

Content

A full-bleed aerial photograph of the terminal labelled with the rail loop dam, inloading facility, inloading to stockyard conveyors, site office, stockyard, the 3.8km jetty, berths and the neighbouring Hay Point Coal Terminal.

Layout Structure

A full-slide aerial photo with teal label boxes placed over each site feature and the title at top left.

Key Visual Elements

  • •Full-bleed aerial photo
  • •Eight teal callout labels
  • •Rail loop dam
  • •Jetty
Page 11
process diagram

DBT Site Layout

Content

DBT covers approximately 3,504,800m2. A numbered table describes ten infrastructure elements, including inloading and stacking at up to 8,100tph, a stockyard with 12 yard machines and 2.0Mt nominal capacity, reclaim rates up to 5,300tph, outloading and shiploaders at up to 8,650tph, and berths for 220,000dwt Capesize vessels. The site plan images on the right are small and some labels are hard to read.

Layout Structure

A numbered infrastructure and description table fills the left, with a site plan and three zoomed inset maps on the right.

Key Visual Elements

  • •Numbered infrastructure table
  • •Site plan with numbered markers
  • •Inloading, stockyard and outloading insets
Page 12
process diagram

Inloading

Content

DBT's inloading systems are the interface between external coal delivery and DBI's stockyard. Trains arrive via three rail operators (Aurizon Operations, Pacific National and OneRail) to three inloading systems (2 x 5,500tph and 1 x 8,100tph), with a stated combined daily capacity of 307,500t and 24/7 operation.

Layout Structure

A bulleted specification list on the left sits beside a large aerial photo of the rail loop and dam on the right.

Key Visual Elements

  • •Rail loop aerial photo
  • •Nested bullet specs
Page 13
process diagram

Stockyard

Content

The stockyard manages customers' coal deliveries and assembles cargoes before shipping. It has 7.5 rows with nominal capacity of 2Mt, 4 stackers up to 8100tph, 3 reclaimers and 5 stacker reclaimers up to 5,300tph, a stockyard length of c.1,176 metres and an average coal residence time of 8.9 days (1 July 2025 to 30 June 2026).

Layout Structure

Two stacked aerial photos of the stockyard occupy the left and a bulleted specification list fills the right.

Key Visual Elements

  • •Two stockyard aerial photos
  • •Equipment specification bullets
Page 14
process diagram

Outloading

Content

The outloading systems transport coal from the stockyard to the shiploader, with surge bins buffering flow. There are 3 outload systems at up to 8,650 tph and 3 surge bins that can store up to 1500t of coal, with certified sampling equipment to test product quality. The aerial photo is low resolution.

Layout Structure

Bullet points occupy the left and a low-resolution annotated aerial of surge bins and a conveyor, with a 'note vehicle size for scale' callout, fills the right.

Key Visual Elements

  • •Annotated aerial photo
  • •Surge bin labels SB1-SB3
  • •Scale callout box
Page 15
process diagram

Offshore

Content

Shiploaders service four berths. The 3.8km jetty supports three conveyor gantries and two roadways, 3 shiploaders have design rates of up to 8,650 tph, and 4 berths can moor 220,000 dwt Capesize vessels. More than 600 ships pass through annually with an average cargo of c.95,000t, tides vary by up to 7m and berth pockets are dredged to about 19 metres.

Layout Structure

A large photo of a ship deck alongside the jetty fills the left and a bulleted list of offshore specifications fills the right.

Key Visual Elements

  • •Ship deck and jetty photo
  • •Offshore specification bullets
Page 16
section divider

NECAP

Content

Section divider introducing the NECAP (non-expansion capital expenditure) part of the presentation.

Layout Structure

A teal rounded panel with the white title sits on the left of a photo of a shiploader and ship at the jetty.

Key Visual Elements

  • •Teal panel
  • •Shiploader and ship photo
  • •Section title
Page 17
data visualization

Organic growth: Non-expansion capital expenditure

Content

NECAP provides an ongoing growth platform, with regular NECAP typically between $30m and $50m a year outside major replacements. $97.8m ($91.3m plus $6.5m IDC) was added to the NECAP Asset Base on 1 July 2026, giving a $0.15/t TIC increase. Charts show the asset base rising from $51.1m in July 2022 to $232.5m in July 2026.

Layout Structure

Five explanatory bullets run across the top and three stacked-bar charts (approved, spent and asset base, in $m) sit side by side beneath.

Key Visual Elements

  • •Three stacked bar charts
  • •Sustaining versus major projects legend
  • •Data labels in $m
Page 18
table

Regular NECAP Projects

Content

As at 1 July 2026 DBI has included over $245m of regular NECAP in the Asset Base since 2021. Four packages are shown: NECAP V ($35m, complete), W ($57m, ongoing), X ($72m, ongoing) and Z ($38m, ongoing), each with project counts and examples.

Layout Structure

Two summary bullets sit above a four-column grid, each column with an image above a package name, project list and status.

Key Visual Elements

  • •Four project columns
  • •Engineering drawing and site photos
  • •Status labels
Page 19
process diagram

Offshore Gallery Wrapping Project

Content

DBT has 3 jetty conveyors (L5, L6, L15), each about 150 x 24m gallery sections, in a corrosive marine environment. The proposed solution is petroleum tape wrapping with indicative capex of approximately $150m over 6 years, and Phase 1 (NX05, $33m) commenced September 2026 and was unanimously approved by customers.

Layout Structure

Issue, Solution and Status text blocks run down the left, with two photos of wrapped gallery steelwork stacked on the right.

Key Visual Elements

  • •Issue, Solution, Status headings
  • •Two wrapped-steel photos
Page 20
timeline

NECAP U: Shiploader 1 (SL1) replacement

Content

The 43-year-old SL1 has been replaced with new shiploader SL1A, with a budget of $165.4m excluding interest during construction, completed on 14 November 2026 on time and on budget. Milestones include delivery on 14 October 2026, first coal on 12 November and handover to Operations on 14 November 2026.

Layout Structure

Four headed text sections (description, cost, status, future projects) run down the left beside a tall photo of the new shiploader.

Key Visual Elements

  • •Shiploader photo
  • •Dated milestone bullets
  • •Section headings
Page 21
timeline

NECAP T: Stacker Reclaimer 2 (SR2) replacement

Content

The 43-year-old SR2 is being replaced by new reclaimer RL4 with a budget of $115.6m excluding interest during construction, running slightly below budget. Construction is due to complete by end of November 2026, handover is expected in January 2027 and SR2 removal is targeted for April 2027.

Layout Structure

Text sections for description, cost and progress run down the left beside a large construction-site photo of RL4.

Key Visual Elements

  • •Construction photo of RL4
  • •Progress milestones
Page 22
data visualization

NECAP supporting revenue uplift

Content

Completion of major NECAP programs is described as driving a step change in TIC. TIC per contract tonne is shown at 3.59, 3.72 and 4.02 for 24/25 to 26/27, with an indicative scenario to 30/31 that is not a forecast. The slide states an anticipated further ~$0.53/t NECAP charge uplift from 1 July 2027 and that every $0.10/t of TIC delivers ~$8.5m of revenue per annum.

Layout Structure

Five bullets fill the left and a stacked bar chart of TIC by year with a callout and legend sits on the right, with three dense footnotes below.

Key Visual Elements

  • •Stacked bar chart 24/25 to 30/31
  • •SL1A and RL4 callout
  • •Four-item legend
  • •Assumption footnotes
Page 23
table

8X Expansion Works

Content

8X is a phased expansion giving a well-defined pathway to 99.1Mtpa, with all primary environmental approvals secured and works wholly within the existing terminal footprint. The three phases total 14.9Mtpa at a cost of $1,583m (FEL3 estimate, P95), and about 35Mtpa of annualised demand is in the access queue as at 31 October 2026.

Layout Structure

Five bullets run across the top, with a three-phase cost table at bottom left and an area chart of the access queue from Jun-26 to Jun-34 at bottom right.

Key Visual Elements

  • •Phase cost table
  • •Access queue area chart
  • •Footnotes on cost basis
Page 24
section divider

Appendices

Content

Section divider introducing the appendix pages.

Layout Structure

A teal rounded panel with the white title sits beside a photo of a red bulk carrier at the jetty.

Key Visual Elements

  • •Teal panel
  • •Bulk carrier at jetty photo
Page 25
process diagram

Roles and Responsibilities

Content

By contracting day-to-day operations to an entity owned by a subset of customers, DBI minimises operational complexity and risk. The matrix assigns duties to DBI (such as financing, NECAP and the access queue), the DBT Operator (such as terminal operation and maintenance), NQBP (pilotage, dredging) and above and below rail parties. Footnote 4 cites 450+ permanent employees and 350+ daily contractors.

Layout Structure

A grid of rounded colour-coded pills in rows by party, with logos at the left, a callout for rail access and six footnotes below.

Key Visual Elements

  • •Colour-coded role pills
  • •DBI, DBCT and NQBP logos
  • •Rail callout
Page 26
appendix

Glossary

Content

Defines terms used in the deck, including $ (Australian Dollar unless otherwise stated), /t (per metric tonne), the 8X Project (expansion to a maximum of 99.1Mtpa), AU, DBI, DBT, NECAP, QCA and TIC.

Layout Structure

Two side-by-side two-column definition tables sit above a wide panoramic photo of ships loading at the jetty.

Key Visual Elements

  • •Two glossary tables
  • •Panoramic jetty photo
Page 27
disclaimer

Disclaimer and important notices

Content

Legal notices stating the information is current as at 24 November 2026, is not an offer or financial product advice, and contains forward-looking statements and AME market data caveats. It confirms all figures are Australian dollars ($ or A$) unless stated otherwise and covers non-IFRS measures. The text is very small and set in two dense columns.

Layout Structure

A two-column page of headed legal paragraphs fills the slide under the title.

Key Visual Elements

  • •Two dense text columns
  • •Bold section subheadings

Frequently Asked Questions

Common questions about this slide and the underlying presentation content.

What is this presentation about?

It is Dalrymple Bay Infrastructure's Dalrymple Bay Terminal Site Visit Presentation dated November 2026. It covers the terminal's history, customers and contracts, Queensland coal port comparison, market outlook, site layout and equipment, the NECAP capital programme and the 8X expansion, across 27 pages.

Where was the original presentation lodged?

Dalrymple Bay Infrastructure (ASX: DBI) lodged it with the Australian Securities Exchange on 24 November 2026. The disclaimer says the information is current as at that date and points readers to DBI's announcements at www.asx.com.au.

What key facts about Dalrymple Bay Terminal does the deck give?

Slide 2 lists 84.2Mt fully contracted on a 100% take or pay basis, a $4.02/t Terminal Infrastructure Charge, 100% pass-through of operating and maintenance costs, 10 customers across 21 mines, a 14% share of 2025 global seaborne met coal exports, and pricing arrangements expiring in 2031. Amounts are Australian dollars.

What does the deck say about the terminal's physical operations?

Pages 10 to 15 describe three rail inloading systems, a stockyard with 12 yard machines and 2.0Mt nominal capacity, outloading and shiploaders at up to 8,650tph, and a 3.8km jetty serving four berths for 220,000dwt Capesize vessels, with more than 600 ships a year on average.

What capital projects and expansion plans are covered?

The NECAP section covers the replacement of shiploader SL1 ($165.4m budget, completed 14 November 2026), stacker reclaimer SR2 with RL4 ($115.6m budget) and a gallery wrapping project of approximately $150m over 6 years. The 8X expansion would add 14.9Mtpa for $1,583m, towards 99.1Mtpa.

How is the deck designed and laid out?

It uses a teal and aqua palette with the DBI logo top right, large aerial and site photographs, full-bleed section dividers with a rounded teal panel, KPI rows, data tables, stacked bar and waterfall charts, annotated site plans and a colour-coded roles matrix. A vertical 'personal use only' watermark appears along the left edge of the pages.

Can I reuse this as a template for an infrastructure or site-visit deck?

Yes as a structural reference. The flow of company snapshot, asset history, customers and contracts, peer comparison, market context, operations walkthrough, capital programme, expansion and appendices suits port, rail, energy or logistics site visits. The source content and branding belong to Dalrymple Bay Infrastructure, so replace them with your own.

Does the deck give investment advice?

No. The disclaimer on slide 27 says the presentation is for informational purposes only, is not an offer or financial product advice, and contains forward-looking statements and third-party AME data that carry uncertainty. The pricing chart on slide 22 is described as an indicative scenario, not a forecast.

2slides

Create Your Own Slides

Turn your ideas into professional presentations in seconds with 2slides AI.

Create World-Class Slides in Seconds

Reference professional designs, choose your style, and generate slides with perfect text rendering. Powered by Nano Banana—start creating your presentation now.

2Slides logo

Your AI Agent for slides. Save time, shine faster with intelligent presentation creation.

Summarize with AI

ChatGPTClaudeGrokPerplexity
All services online

Products

Features

Gallery

Templates

Integrations

Resources

Comparison

© 2026 2slides. All rights reserved.