Логотип 2Slides
Preview

Resolute Mining Q3 2026 Activities Presentation

25 слайдов

Входит в коллекцию Примеры презентаций для инвесторов · Примеры презентаций для инвесторов из Австралии

Resolute Mining Q3 2026 Activities Presentation: the 25-slide quarterly activities report deck from ASX-listed African gold producer Resolute Mining Limited (ASX: RSG), dated 29 October 2026 and lodged with the ASX. It covers the September 2026 quarter (Q3 = July to September 2026; Resolute reports on a calendar year): 44,398 oz gold poured at a Group AISC of US$2,506/oz, Q3 revenue of US$143 million, EBITDA of US$64 million, net cash of US$276 million, the Doropo construction project in Côte d'Ivoire, the ABC and La Debo growth projects, and the Syama (Mali) and Mako (Senegal) operations.

1 лайков
0 загрузок

Использует обложку этой презентации как образец стиля для слайдов с вашим содержанием. Или выберите любую страницу ниже, чтобы взять за образец её макет.

Быстрая навигация

Теги

Resolute Mining
Resolute Mining Q3 2026
RSG
ASX
Quarterly activities report

Поделиться слайдами

Описание

Основная тема

Resolute Mining Q3 2026 Activities Presentation: the 25-slide quarterly activities report deck from ASX-listed African gold producer Resolute Mining Limited (ASX: RSG), dated 29 October 2026 and lodged with the ASX. It covers the September 2026 quarter (Q3 = July to September 2026; Resolute reports on a calendar year): 44,398 oz gold poured at a Group AISC of US$2,506/oz, Q3 revenue of US$143 million, EBITDA of US$64 million, net cash of US$276 million, the Doropo construction project in Côte d'Ivoire, the ABC and La Debo growth projects, and the Syama (Mali) and Mako (Senegal) operations.

Ключевые преимущества

  • •Real ASX quarterly activities deck from a mid-tier African gold miner, showing how a producer reports one quarter of mining, processing, cost and cash data in 25 slides
  • •Clear operating vs financial metrics split on a single summary slide: gold poured, AISC and capex beside gold sold, realised price, EBITDA, operating cash flow and net cash
  • •Per-mine operating tables (Syama, Mako) comparing September quarter, June quarter, 9M 2026 and 9M 2025 for ore mined, grade, recovery, gold poured, gold sold, capex and AISC
  • •Project Gantt charts for Doropo construction (first gold H1 2028), the ABC study schedule (completion Q4 2027) and the Mako Life Extension Project (through 2029)
  • •Net cash waterfall from US$317.4 million (1 July 2026) to US$276.1 million (30 September 2026), a reusable layout for any quarterly cash bridge
  • •Navy-and-gold mining design with full-bleed site photography as country section dividers (Côte d'Ivoire, Mali, Senegal)

Целевая аудитория

  • •Gold and mining equity investors and analysts following ASX-listed producers
  • •Investor relations teams at mining and resources companies preparing quarterly activities reports
  • •Mining finance students learning AISC, ore reserves, MRE and project development reporting
  • •Consultants and bankers covering West African gold projects
  • •Presentation designers who need a resources-sector quarterly update template

Случаи использования

  • •Studying how an ASX gold miner structures a quarterly activities report presentation
  • •Building a quarterly operations update with per-asset production and cost tables
  • •Presenting a mine construction project status with a timeline Gantt and site photos
  • •Reporting a Mineral Resource Estimate update with a resource table and drill plan
  • •Creating a net cash waterfall and financial highlight tiles for an earnings or activities call
  • •Benchmarking Resolute's Q3 2026 AISC, realised gold price and liquidity against peers

Уникальные ценностные предложения

  • •Original company deck lodged with the ASX, not a mock-up, available as PDF and as an editable PPTX converted from the PDF
  • •Every one of the 25 slides is summarised below with its numbers, so the content is searchable without opening the file
  • •Covers a full growth story in one quarter: two producing mines, one mine under construction, two development projects and a 500 koz+ production pathway
  • •All dollar values are in US dollars as stated in the deck's disclaimer, a useful example of an Australian-listed company reporting in USD

Страницы слайдов (25)

Подробный просмотр каждой страницы слайда, включая макет, ключевой контент и визуальные элементы.

Страница 1
Title slide

Cover: Q3 2026 Activities Report

Содержание

Title slide for Resolute's Q3 2026 Activities Report dated 29 October 2026, with the Resolute R-and-hammer logo and wordmark on a navy panel beside a photo of an excavator loading a haul truck over a pile of broken ore.

Структура макета

Split layout: left half solid navy with logo, yellow rule, yellow title and date; right half full-height mining photograph.

Ключевые визуальные элементы

  • •Resolute logo and wordmark
  • •Yellow title text
  • •Excavator and haul truck photo
  • •Vertical 'For personal use only' ASX watermark
Страница 2
Disclaimer / legal

Disclaimer

Содержание

Three-column legal disclaimer: information current as at the date of the presentation, forward-looking statements, JORC Code reporting of Ore Reserves and Mineral Resources (referencing the 5 March 2026 Ore Reserves and Mineral Resource Statement, the 15 December 2025 Doropo DFS Update and the 22 July 2026 ABC MRE), ASX Listing Rules 5.19 and 5.23 confirmations, AISC calculated per World Gold Council guidelines as non-IFRS information, 2026 production guidance of 205,000-225,000 oz at AISC of US$2,250-2,350/oz (Syama Operational Update, 21 September 2026), and the statement that all dollar values are in US dollars unless otherwise stated; authorised for release by CEO Chris Eger.

Структура макета

Dense three-column body text under a large white heading with a yellow underline on a navy background.

Ключевые визуальные элементы

  • •Three text columns
  • •Yellow heading rule
  • •Small logo top right
Страница 3
Speaker / team introduction

Speakers

Содержание

Lists the call presenters: CEO Chris Eger, COO Gavin Harris, CFO Dave Jackson, and Corporate Development and Investor Relations lead Matty O'Toole-Howes.

Структура макета

Full-bleed photo of a terraced open pit with a bullet list of names overlaid in white bold text and a yellow heading.

Ключевые визуальные элементы

  • •Open-pit mine photograph
  • •Four bulleted speaker names
  • •Yellow 'Speakers' title
Страница 4
Executive summary / KPI dashboard

Q3 Activities Summary

Содержание

One-page quarter summary. Operations: year-to-date TRIFR 0.85 with four recordable injuries in Q3; Syama 31,777 oz at AISC US$2,596/oz; Mako 12,621 oz at AISC US$1,516/oz; on track for revised 2026 guidance of 205-225 koz at AISC US$2,250-2,350/oz. Projects: Doropo on track and on budget with US$52.9 million capital spend in the quarter; ABC over 23,000 m drilled; La Debo MRE up 44% from 643 koz to 927 koz; Syama Sulphide Conversion Project commissioning nearing completion; Mako Life Extension Project advancing ESIA and Bantaco drilling. Corporate: Doropo financing completed with US$260 million local bank debt in Côte d'Ivoire, US$29 million drawn. Operating metrics box: 44,398 oz gold poured, US$2,506/oz Group AISC, US$85 million capex. Financial metrics box: 33,035 oz gold sold, US$4,325/oz average realised price, US$64.0 million EBITDA, US$55.8 million operating cash flow, US$276.1 million net cash.

Структура макета

Two-column dashboard: left column of grouped bullet lists (Operations, Projects & Exploration, Corporate); right column with a cream Operating Metrics card above a grey Financial Metrics card.

Ключевые визуальные элементы

  • •Operating Metrics card
  • •Financial Metrics card
  • •Bold asset names in bullets
  • •Yellow underline accents
Страница 5
Growth strategy / data visualisation

Pathway to 500+ koz p.a. within four years

Содержание

Production growth chart: 277 koz achieved in 2025, 205-225 koz guidance for 2026, 250-275 koz target for 2027 (ABC feasibility workstreams), then rising 2028-2029 with Doropo in production toward a target of more than 500 koz per year beyond 2030 including ABC and future growth opportunities (La Debo, Guinea exploration, Doropo expansions, optimising Mali). Donut charts show production mix moving from Syama 64% / Mako 36% in 2025 to Syama 40% / Doropo 42% / Mako 18% in 2029. AISC bar chart (US$/oz): Syama 2,350 and Mako 1,700 at 2026E guidance midpoint, Doropo 1,472 life-of-mine average. Footnotes reference JORC-compliant reserves and source announcements.

Структура макета

Stacked bar timeline across the top, two donut charts and an AISC bar chart in the lower half, with outlined callout boxes on the right; footnotes at bottom.

Ключевые визуальные элементы

  • •Stacked production bars 2025-beyond 2030
  • •Orange upward arrow
  • •Two donut charts
  • •AISC bar chart
  • •Checklist callout boxes
Страница 6
Section divider

Section divider: Côte d'Ivoire

Содержание

Section break introducing the Côte d'Ivoire assets (ABC, La Debo and Doropo), over a photo of geologists logging drill core.

Структура макета

Full-bleed photograph with large white section title and a short yellow rule on the left.

Ключевые визуальные элементы

  • •Core logging photo
  • •Large white country title
  • •Logo top left
Страница 7
Project overview with map

ABC Project

Содержание

ABC is being advanced to become Resolute's fourth mine in West Africa and second in Côte d'Ivoire. Since the July 2026 MRE update, focus is on infill drilling and expanding the resource footprint; 23,900 m drilled in Q3 2026 with 11 rigs operating; metallurgical studies and the Environmental and Social Impact Assessment started in Q3 2026. A map shows the Faraka Nafana, Kona (Moya, Kona Central, Kona South), Windou, Gbemanzo, Kato and Gouramba permits.

Структура макета

Text bullets on the left; permit map with inset country map and legend on the right.

Ключевые визуальные элементы

  • •Tenement map with granted and application claims
  • •Côte d'Ivoire inset map
  • •Nested bullet list
Страница 8
Timeline / roadmap

ABC Project: Next Steps

Содержание

Updated MRE targeted for Q1 2027; the next twelve months cover technical studies, environmental and social baseline work, metallurgical testwork and site infrastructure upgrades. Study schedule Gantt (Q4 2026-Q4 2027): Mineral Resource Update, ESIA Phase 1, technical studies (hydro, geotech, metallurgical), mine planning and optimisation, with expected study completion in Q4 2027. A drill plan shows completed Q3 and pending holes at Kona Central and Kona South.

Структура макета

Left: bullets above a quarterly Gantt chart with a star milestone. Right: drill-hole plan with zoom insets and geology legend.

Ключевые визуальные элементы

  • •Gantt chart with blue bars
  • •Yellow star milestone
  • •Drill plan map with Kona insets
Страница 9
Project overview with map

La Debo Project

Содержание

La Debo is an MRE-stage development project in Côte d'Ivoire offering longer-term organic growth. 15,867 m of diamond drilling in 2026 led to an October 2026 MRE update at G3S; the programme aimed to drill out a 600 m strike panel and extended higher-grade mineralisation down dip at G3S. Map shows targets G3N, G3S, G2, G4, F1, F2, Main, LD and LDS within the La Debo, Okroyou and Serihio permits.

Структура макета

Bullets on the left, geological permit map with legend and inset on the right.

Ключевые визуальные элементы

  • •Geology map with target markers
  • •Permit outlines
  • •Country inset
Страница 10
Data table / resource estimate

La Debo Project: MRE Update

Содержание

October 2026 MRE update for G3 South after additional drilling (G3 North unchanged): G3S resource up 75% to 14.9 Mt at 1.4 g/t; a higher-grade core of 4.2 Mt at 2.9 g/t Au for 397 koz. Inferred MRE table (0.5 g/t cut-off, unconstrained): G3 North 8.6 Mt at 0.9 g/t for 0.26 Moz; G3 South 14.9 Mt at 1.4 g/t for 0.67 Moz; total 23.5 Mt at 1.2 g/t for 0.93 Moz. Plan view lists drill intercepts such as 23 m at 3.38 g/t Au including 1 m at 61.34 g/t (LBDD0078) and 25 m at 1.91 g/t including 5 m at 6.68 g/t (LBDD0077).

Структура макета

Bullets and a blue-header resource table on the left; annotated drill plan with assay callouts and colour legend on the right.

Ключевые визуальные элементы

  • •Mineral resource table
  • •Drill intercept callouts
  • •Block model colour legend
  • •Section lines A-A', B-B', C-C'
Страница 11
Project status / timeline

Doropo

Содержание

Doropo construction: no LTIs since construction began; over 800 people on site; Operations General Manager hired; stage 1 accommodation delivered; key earthworks, water storage and tailings earthworks and plant concrete works under way; SMP and electrical packages progressed; tender for a 30 MW solar plant completed; wet season navigated on schedule. Timeline: on track and on budget for first gold in H1 2028; US$52.9 million capital spend in Q3; about US$315 million (61%) of total capex committed. Gantt (Q1 2026-Q4 2028) covers early works, long-lead procurement, construction, commissioning, first gold (Q2 2028) and ramp-up.

Структура макета

Two columns: left bullet list of Q3 activities, right project timeline bullets above a quarterly Gantt chart.

Ключевые визуальные элементы

  • •Construction Gantt chart
  • •Yellow star for first gold
  • •Yellow ramp-up bar
Страница 12
Image gallery / progress photos

Doropo Construction Activities

Содержание

Photo page of construction progress: concrete batch plant commissioned, ring beam foundations, mill area raft foundation, and a concrete pour on the CIL Tank No. 8 ring beam.

Структура макета

Four aerial and ground photos in a staggered grid with yellow borders and short captions.

Ключевые визуальные элементы

  • •Four site photographs
  • •Yellow photo frames
  • •Caption labels
Страница 13
Action plan / next steps

Doropo Planned Activities

Содержание

Remainder-of-year plan: complete the construction camp and start mine village installation; finish plant-site and mine services bulk earthworks early in Q4 and continue the TSF, water storage dam and water harvesting dam; concrete works across CIL, milling, thickener, reclaim and crushing; mobilise the CIL tank contractor; complete water bores and borefield piping; award major mechanical, electrical, mining and solar packages; progress SMP and E&I installation contracts; detailed engineering and procurement; owner's team and operational readiness.

Структура макета

Single-column bullet list under a large heading on navy background.

Ключевые визуальные элементы

  • •Nine bullet points
  • •Clean text-only layout
Страница 14
Exploration opportunity

Doropo Potential Expansion: Kilosegui

Содержание

Exploration drilling began in Q3 at the Kilosegui deposit about 30 km from the Doropo process plant: an initial 20,000 m RC and step-out diamond programme to test down-dip extensions. Kilosegui holds the largest Ore Reserve in the updated DFS mine plan (21.8 Mt at 1.22 g/t Au for 856 koz at a US$1,950/oz gold price), sits on a 6 km mineralised trend open down dip, and study work is assessing a second standalone processing plant and tailings facility.

Структура макета

Bullets on the left, satellite image with block model and planned drill traces on the right.

Ключевые визуальные элементы

  • •Satellite image with block model overlay
  • •Red planned drill traces
  • •Image caption
Страница 15
Section divider

Section divider: Mali

Содержание

Section break for the Mali operations (Syama), shown with an underground drill rig in a meshed tunnel.

Структура макета

Full-bleed dark underground photograph with white section title.

Ключевые визуальные элементы

  • •Underground mining photo
  • •Large white title
Страница 16
Operations data table

Syama Operation

Содержание

Syama produced 31.8 koz at AISC US$2,596/oz, in line with the September operational update. Underground mining was constrained early in Q3 by explosive availability and wet-area blasting; emulsion supply improved and an on-site emulsion plant is being commissioned. The SSCP roaster upgrade was commissioned, with the secondary crusher and ball mill to follow. Q4 production expected to rise to 45-50 koz. Q3 capex US$18.6 million; full-year capex expected below the US$70-85 million guidance. Table (Sep Q vs Jun Q vs 9M 2026 vs 9M 2025): underground ore mined 490,070 t at 2.09 g/t; open pit 300,182 t at 2.11 g/t; sulphide ore processed 655,115 t at 2.15 g/t, 72% recovery, 30,439 oz poured, 20,762 oz sold; oxide 53,741 t at 0.61 g/t, 1,338 oz poured; 9M 2026 AISC US$2,459/oz vs US$2,092/oz in 9M 2025.

Структура макета

Bullet commentary on the left; detailed operating table on the right grouped into Mining, Processing and Cost bands.

Ключевые визуальные элементы

  • •Multi-period operating table
  • •Vertical band labels (Mining, Processing, Cost)
  • •Navy table headers
Страница 17
Section divider

Section divider: Senegal

Содержание

Section break for the Senegal operation (Mako), shown with a photo of the Mako processing plant beside a waste dump.

Структура макета

Full-bleed processing plant photograph with white section title.

Ключевые визуальные элементы

  • •Process plant photo
  • •Large white title
Страница 18
Operations data table

Mako Operation

Содержание

Mako produced 12.6 koz at AISC US$1,516/oz, in line with expectations; year-to-date production 43.7 koz keeps Mako on track for 55-65 koz full-year guidance. AISC came in below the US$1,600-1,800/oz guidance range thanks to lower rehandle, processing and maintenance costs; sustaining capital of US$1.2 million for plant maintenance. Table: ore processed 504,295 t at 0.85 g/t and 91% recovery; gold poured 12,621 oz; gold sold 10,935 oz; capex US$3.3 million; 9M 2026 gold poured 43,733 oz vs 82,140 oz in 9M 2025 and AISC US$1,579/oz vs US$1,180/oz.

Структура макета

Bullets on the left, compact seven-row operating table on the right.

Ключевые визуальные элементы

  • •Operating summary table
  • •Quarter and 9M comparison columns
Страница 19
Timeline / roadmap

Mako Life Extension Project (MLEP)

Содержание

Q3 2026 MLEP work focused on permitting, ESIA public hearings and the Relocation Action Plan (RAP), including agreeing the relocation package with the community; exploration permit transfers expected in Q4 2026 and exploitation permits for both deposits in H1 2027. Next steps: agree the Tomboronkoto relocation package and the Bantaco livelihood restoration approach to complete RAP Phase 1 by end Q1 2027, and finalise new village design and tender documents for RAP Phase 2. Gantt (Q3 2026-Q4 2029): technical studies, permitting, plant modifications, relocation and road diversion, Mako stockpile processing, Bantaco mining and Tomboronkoto mining.

Структура макета

Bullets (Q3 activities and next steps) on the left; quarterly Gantt chart with blue, grey and yellow bars on the right.

Ключевые визуальные элементы

  • •Multi-year Gantt chart
  • •Colour-coded workstreams
  • •Quarter column headers
Страница 20
Section divider

Section divider: Financial Summary

Содержание

Section break for the financial results, over a photo of articulated haul trucks on a muddy haul road.

Структура макета

Full-bleed photograph with white section title and yellow rule.

Ключевые визуальные элементы

  • •Haul truck photo
  • •Large white title
Страница 21
KPI highlights

Financial Highlights

Содержание

Six headline figures: Q3 revenue US$143 million (unaudited), Q3 EBITDA US$64 million (unaudited), net cash US$276 million, available liquidity US$480 million, Q3 Group AISC US$2,506/oz and Q3 average realised gold price US$4,325/oz.

Структура макета

Three staggered outlined boxes, each with a yellow circular icon (money bag, gold bars, pickaxe) and two large figures with yellow underlines.

Ключевые визуальные элементы

  • •Yellow circular icons
  • •Large metric numbers
  • •Staggered outlined panels
Страница 22
Financial chart / cash bridge

Cash Flow Summary

Содержание

Total capital and exploration spend of US$85 million as Doropo construction and exploration ramped up; working capital inflow of US$6 million; net cash of US$276 million at quarter-end; US$260 million of local bank debt secured for Doropo with US$29 million drawn; existing balance sheet, operating cash flow and local debt seen as sufficient to fund Doropo. Waterfall: net cash US$317.4 million at 1 July 2026, plus operating cash flows 55.8 and working capital 6.2, less VAT paid 9.1, capex 74.8, exploration 10.6 and minority shareholder dividend 8.8, ending at US$276.1 million on 30 September 2026.

Структура макета

Bullets on the left over a light background with a rock image; net cash waterfall chart on the right.

Ключевые визуальные элементы

  • •Waterfall chart
  • •Navy start/end bars
  • •Yellow inflow bars
  • •Grey outflow bars
Страница 23
Section divider

Section divider: Conclusion

Содержание

Section break before the closing summary, with three workers in high-visibility gear walking along a red dirt road.

Структура макета

Full-bleed photograph with white section title.

Ключевые визуальные элементы

  • •Field workers photo
  • •Large white title
Страница 24
Conclusion / key takeaways

Resolute Summary

Содержание

Closing takeaways: Doropo construction fully funded, on track and on budget; a strong organic growth pipeline across the portfolio (ABC and expansion studies); net cash of US$276 million; a broader geographic footprint for long-term growth; positioned to exceed 500 koz of annual gold production by the end of 2028.

Структура макета

Left navy panel with five yellow arrow bullets; right panel photo of gloved hands holding a gold bar.

Ключевые визуальные элементы

  • •Yellow arrow bullets
  • •Gold bar photograph
  • •Logo top right
Страница 25
Closing slide

Closing: Resolute logo

Содержание

Back cover with the large Resolute logo and wordmark and the company website www.rml.com.au.

Структура макета

Solid navy background with oversized logo and wordmark, yellow bottom rule.

Ключевые визуальные элементы

  • •Large R-and-hammer logo
  • •Resolute wordmark
  • •Website URL

Часто задаваемые вопросы

Распространенные вопросы об этом слайде и основном содержании презентации.

What is the Resolute Mining Q3 2026 Activities Presentation?

It is the 25-slide deck Resolute Mining Limited (ASX: RSG) released with its Q3 2026 Activities Report on 29 October 2026 and lodged with the ASX. It covers safety, production and costs at Syama and Mako, Doropo construction, the ABC and La Debo projects, and the quarter's financial results.

Which period does Q3 2026 cover for Resolute?

Resolute reports on a calendar year, so Q3 2026 is the September 2026 quarter, July to September 2026. This differs from many ASX companies whose financial year runs July to June.

What currency are the figures in?

US dollars. Although Resolute is listed on the ASX, the deck's disclaimer states that all dollar values are in United States dollars unless otherwise stated, so the $143 million revenue and $2,506/oz AISC are US$ figures.

What were Resolute's key Q3 2026 numbers?

44,398 oz of gold poured and 33,035 oz sold, Group AISC of US$2,506/oz, an average realised gold price of US$4,325/oz, revenue of US$143 million and EBITDA of US$64 million (both unaudited), operating cash flow of US$55.8 million, net cash of US$276.1 million and available liquidity of US$480 million.

What is the status of the Doropo project?

Doropo in Côte d'Ivoire is under construction, on track and on budget for first gold in H1 2028. Q3 capital spend was US$52.9 million, about US$315 million (61%) of capex is committed, and US$260 million of local bank financing has been secured with US$29 million drawn.

What is Resolute's 2026 guidance and long-term production target?

Revised 2026 guidance is 205-225 koz at AISC of US$2,250-2,350/oz. The deck sets out a pathway to more than 500 koz a year, with Doropo in production and ABC and other growth options, and the closing slide says Resolute is positioned to exceed 500 koz annually by the end of 2028.

Can I download this deck as an editable PowerPoint?

Yes. The page offers the original PDF and a PPTX version converted from that PDF, so slide text, tables and Gantt charts can be edited. Conversions from PDF may need minor layout fixes, and the original remains the authoritative ASX document.

How can I reuse this layout for my own mining quarterly report?

Useful patterns include the split operating/financial metrics summary on slide 4, the per-mine operating tables on slides 16 and 18, the construction and study Gantt charts on slides 8, 11 and 19, and the net cash waterfall on slide 22. Replace the data with your own and keep the country section dividers to organise assets by jurisdiction.

Источники и дополнительные материалы

2slides

Create Your Own Slides

Turn your ideas into professional presentations in seconds with 2slides AI.

Создавайте Слайды Мирового Класса за Секунды

Используйте профессиональные дизайны, выберите свой стиль и генерируйте слайды с идеальной отрисовкой текста. На базе Nano Banana—начните создавать свою презентацию прямо сейчас.

2Slides logo

Ваш AI-агент для слайдов. Экономьте время, сияйте быстрее с интеллектуальным созданием презентаций.

Резюмировать с помощью ИИ

ChatGPTClaudeGrokPerplexity
Все сервисы работают

Продукты

Функции

Галерея

Шаблоны

Интеграции

Ресурсы

Сравнение